Sendje Hydropower Plant Project

Sendje HPP is a project with installed capacity 200 MW, which will supply the continental part of the Republic of Equatorial Guinea and the neighboring countries, improving the standard of living and comfort, as well as ensuring the economic growth of the region. The project is executed by order of the Government of the Republic of Equatorial Guinea.

Main features of the project:

  1. Installed capacity 200 MW, 4 units with a unit capacity 50 MW.
  2. Voltage of output 220 kV.
  3. Average annual output 1,402 million kWh.
  4. Nominal head 67.5 m.
  5. Reservoir:
    • Reservoir surface area 21.57 km2
    • Normal reservoir water level 88 m.
    • Reservoir net storage 60 million m3.